Nuoshui Avenue's Fuyang tunnel to be completed in 2022

chinadaily.com.cn | Updated: Oct 26,2020
1 2 3 4 5

Tongjiang county recently committed nearly 100 workers, eight compressors, four shotcrete trucks, four loaders and two excavators to aid in the construction of the Fuyang tunnel on Nuoshui Avenue.

The tunnel is expected to be completed in mid-2022.

To date, 60 meters of the tunnel's left hole and 20 meters of its right hole have been dug. 

The tunnel is a separated super-long tunnel, with the left branch stretching 3,695 meters and the right branch stretching 3,658 meters. It is a crucial development of the Nuoshui Avenue project, and its smooth progress will lay a solid foundation for the overall construction of Nuoshui Avenue.